Construction business loans have to solve one problem before anything else: you pay for labor and materials weeks or months before the owner or general contractor pays you, and a slice of every invoice is held back as retainage until the job closes. The products that fit that shape are a line of credit, receivables financing, equipment financing and, for larger or public work, SBA CAPLines. The products that usually do not fit are daily-payment cash advances, which drain the same cash flow you are trying to protect.
This guide is part of our business loans by industry series. Select Loan Advisors is an advisory firm, not a lender. We compare contractor loans across a network of funding partners, with one application and no hard credit pull to see options, and we are paid by the funding partner when a deal closes.
Three features of construction billing drive every financing decision.
Progress billing and retainage. You invoice monthly against a schedule of values. The owner or GC commonly withholds 5% to 10% of each payment as retainage until substantial completion or final acceptance. On a $400,000 job with 10% retainage, $40,000 of your money sits with the owner until close-out, which can be months after your last day on site. That is your profit margin, or most of it, parked.
Pay-when-paid and pay-if-paid clauses. Many subcontracts pay you when (or only if) the owner pays the GC. Net-30 on paper becomes 45 to 75 days in practice. Federal work is an exception: under the Prompt Payment Act rules in 5 CFR 1315, agencies owe payment 30 days after a proper invoice, with interest after that, and prime contractors must pass payment down to subs on a similar clock.
Seasonality. Revenue concentrates in eight or nine months while fixed costs run twelve. Underwriters read your bank statements month by month for exactly this reason.
Amounts, rates and terms shown are illustrative examples, not an offer or a quote. Select Loan Advisors is not a lender; funding partners set all terms. See how we're compensated.
| Need | Best-fit product | Illustrative cost | Why it fits |
|---|---|---|---|
| Cover payroll and materials between draws | Business line of credit | Bank lines roughly prime + 1.75% to prime + 9.75% (8.50% to 16.50% at 6.75% prime); online lines higher | Revolving; draw when you bill, repay when you are paid |
| Convert slow receivables to cash | Invoice factoring | Construction advances often 70% to 80% of the invoice; fees roughly 2.5% to 4.5% per 30 days | Approval rests on your customer's credit, not yours; works for newer companies |
| Buy or replace equipment | Equipment financing | Most 2026 equipment loans roughly 10% to 20%; 2 to 7 year terms | The machine is the collateral; preserves the line for operations |
| Fund a specific large contract | SBA CAPLines (Contract or Builders) | SBA 7(a) rate caps: at 6.75% prime, 9.75% to 13.25% depending on size | Up to $5M; Builders line runs 60 months plus construction time |
| Expand, acquire, or buy a yard | SBA 7(a) or term loan | Bank term loans averaged about 6.75% to 7.19% in Q4 2025 | Long amortization for long-lived investments |
Retainage is hard to finance directly because it is contingent on close-out; most lenders exclude it from a borrowing base. Size your line to carry operations without it.
A surety bond guarantees the project owner that you will perform and pay your subs and suppliers. It is not a loan; no money comes to you. Sureties underwrite working capital, net worth, backlog and CPA-prepared financials much as a bank does. Where the two interact:
Ask your bonding agent how a loan will land on your financial statements before you sign. We will ask the same question.
A composite example with rounded numbers, not a client.
A mechanical subcontractor bills about $100,000 a month across three jobs. Weekly payroll and materials run $75,000 a month. GCs pay in 60 days on average, and 10% retainage is held on every invoice.
The gap. At any moment, roughly two months of billings ($200,000) are outstanding, plus accumulated retainage of $10,000 a month that will not arrive until each job closes. Cash needed to bridge: about $150,000 of operating costs before the first dollar of the first invoice lands.
Option A: $150,000 line of credit at an illustrative 12%. If the average drawn balance is $100,000 for the year, interest is about $12,000, or 1% of annual billings. Requires roughly 2 years in business, 680+ credit, and clean statements.
Option B: Factor $100,000 of invoices a month at a 75% advance and 3% per 30 days. Advance received: $75,000 within a day or two of invoicing. If invoices take 60 days to pay, the fee is about $6,000 per $100,000 batch, roughly $72,000 a year, or 6% of billings. Expensive, but available to a company with 8 months of history and a 620 credit score, and it scales with the work.
Option C: A daily-payment advance of $150,000 at a 1.35 factor rate. Payback $202,500 over about 6 months: $52,500 in cost and roughly $1,558 pulled from the account every business day, including days when no draw came in. APR-equivalent roughly 70% on the simple approximation, higher on a true amortized basis. This is the option sold to contractors most often, and it fits their cash flow least.
The advisory answer: Option A if the file qualifies; Option B (see our guide to factoring receivables) as a bridge while building toward A; Option C only for a short, specific, high-margin gap with a known payoff date, and usually not even then.
Beyond the standard business loan requirements, expect lenders to ask for:
Seasonal contractors do better applying for a line in the busy season, when statements look strongest, and sizing it to carry the slow season.
One application, a soft credit pull, and an advisor who asks for your schedule of contracts before recommending anything. We go to the funding partners that actually want construction files, a shorter list than most brokers admit, and show every offer as an APR-equivalent and total dollar cost. Read more about how business loan brokers work. Funding partners pay us when a deal closes; there is no fee to you.
Yes, though the menu is shorter. Equipment financing is available early because the asset secures the loan. Invoice factoring depends mostly on your customers' credit, so a subcontractor with six to twelve months of history and reputable GCs can often qualify. Bank lines and SBA loans generally want two years of financials, so plan those as the second step.
Rarely, and never cheaply. Retainage is contingent on completion and acceptance, so most lenders and factors exclude it from the borrowing base. The practical approach is to size your line of credit or factoring facility to carry operations while retainage accumulates, and to negotiate retainage reductions or early release for completed scopes where the contract allows.
It can. Sureties measure working capital and net worth. A short-term loan adds a current liability and can shrink your bonding program, while a properly structured term loan or equipment loan usually does not, and can even improve the ratios sureties watch. Ask your bonding agent before you borrow, and expect us to ask how the loan will land on your balance sheet.
A line of credit is a loan secured by your business, drawn and repaid as you need it; it is cheaper but requires stronger credit and time in business. Factoring is the sale of specific invoices to a factor at a discount; it costs more per dollar but is approved mainly on your customer's credit, works for newer companies, and grows with your billings. Many contractors start with factoring and graduate to a line.
Usually not. Advances pull a fixed amount from your account daily or weekly regardless of whether a draw came in, which is exactly wrong for progress billing. The CFPB describes them as structured as a sale of future income with a factor rate, and APR-equivalents commonly run far above line-of-credit or factoring costs. They can make sense for a short, high-margin gap with a known payoff date, and rarely otherwise.
Send us your schedule of contracts and six months of statements and an advisor will tell you which products you qualify for today, which you could qualify for in six months, and what each costs. If waiting is the better answer, we will say so.